Photo taken on March 22, 2018 shows the construction site of Thailand-China High Speed Train project in Pak Chong, Thailand. Construction of the first section of Thailand-China High Speed Train project has been running smoothly, or 7 percent completed, Thanin Somboon, Director-General of Thailand's Department of Highways said on Thursday at the construction site here. (Xinhua/Rachen Sageamsak)
PAK CHONG, Thailand, March 22 (Xinhua) -- Construction of the first section of Thailand-China High Speed Train project has been running smoothly, or 7 percent completed, Thanin Somboon, Director-General of Thailand's Department of Highways said on Thursday at the construction site here.
The clearing and grubbing of the first 3.5-kilometer section is finished in the main, contributing to a 7 percent completion of the section, said Thanin at a press tour to where the project began last December.
"The highway department is confident to finish the 3.5-kilometer section within four months, or before August, once we are fully funded," said the director-general.
So far, the cooperation between China and Thailand has been going well, which would be a referential experience for the construction of future sections, Thanin emphasized.
Thailand and China jointly inaugurated the construction of Thailand's first high-speed railway from Bangkok to northeastern province of Nakhon Ratchasima, or the 253-km first phase of Thailand-China high speed railway last December.
Once completed, the railway with a maximum speed of 250 km per hour will be the first high-speed railway of Thailand.